Sprint PlanningScoring Guide
What each question measures, why it matters, and how to improve your score.
Sprint Planning Assessment
The breakdown below maps each question on the Sprint Planning Assessment to a real team habit, explains why it counts toward the score, and gives you a concrete next step if your team scored low.
Score Interpretation
How to read your total maturity score (0 to 100).
1 to 20: Struggling. Sprint planning is largely reactive. The backlog is not ready when planning starts, goals are inconsistent or absent, and the team is often surprised by scope or capacity issues mid sprint.
21 to 40: Developing. Some planning discipline exists, but it is inconsistent from sprint to sprint. Backlog readiness and sprint goals depend heavily on who is in the room that day.
41 to 60: Norming. The team has a repeatable planning rhythm. Backlog readiness and sprint goals show up most sprints, though commitment confidence and demo consistency still vary.
61 to 80: Performing. Planning is a reliable, well understood ritual. The backlog is consistently ready, goals are clear, and the team demonstrates work on a predictable cadence.
81 to 100: Thriving. Sprint planning is a strength the team can count on. The backlog stays several sprints ahead, ownership of stories is clear, and demos happen without fail.
Backlog Visibility
Is the backlog visible to the whole team before sprint planning begins?
Why it matters: A backlog the team cannot see or has not reviewed forces planning conversations to happen for the first time in the room, which slows decisions and buries risks that should have surfaced earlier. Teams that keep the backlog visible between sprints walk into planning already knowing what is coming.
To improve your score: Share the backlog view with the whole team on an ongoing basis, not just during planning, and ask team members to flag questions or concerns before the session starts.
Backlog Readiness
How ready is the backlog for sprint planning, in terms of grooming, estimation, and prioritization?
Why it matters: An unready backlog turns sprint planning into a grooming session, which eats the time meant for sequencing and commitment. Teams with a consistently ready backlog spend planning time on decisions, not discovery.
To improve your score: Run backlog refinement as its own separate event before sprint planning, and hold the top of the backlog to a clear definition of ready.
Story Splitting
Are large or unclear stories split into smaller, well-defined pieces before the team commits to them during planning?
Why it matters: Oversized or vague stories are a common source of mid-sprint surprises: they hide unknowns, make estimation unreliable, and often cannot be finished in a single sprint even when the team commits to them in good faith. Splitting a story before commitment forces the team to actually understand what is inside it.
To improve your score: Add a story-splitting check to your Definition of Ready, and if a story cannot be described in one sentence or estimated with confidence, break it down before it goes into the sprint.
Definition of Done Reference
Does the team check candidate stories against a shared Definition of Done before committing to them in planning?
Why it matters: Without a shared Definition of Done, “done” means something different to every person on the team, which shows up later as rework, missed testing, or disputes about whether a story is really finished. Checking stories against the Definition of Done during planning catches gaps before they become sprint-end surprises.
To improve your score: Keep the Definition of Done visible during planning and have the team explicitly confirm each story can realistically meet it before it is pulled into the sprint.
Product Owner Engagement
Is the Product Owner present and actively answering questions throughout sprint planning?
Why it matters: Planning conversations move fast, and an absent or distracted Product Owner forces the team to guess at priorities, acceptance criteria, and trade-offs, guesses that often turn out wrong. A present, engaged Product Owner keeps clarifying decisions in the room instead of stalling them until later in the sprint.
To improve your score: Protect the Product Owner’s calendar for the full planning event, not just the opening minutes, and make it normal for the team to stop and ask a clarifying question the moment it comes up.
Sprint Goals
Does the team consistently set and align on a clear sprint goal?
Why it matters: A sprint without a stated goal is just a list of tickets. A clear goal gives the team a shared reason to trade off scope when priorities shift mid sprint, and it gives stakeholders a plain answer to “what are we trying to accomplish this sprint.”
To improve your score: Write the sprint goal down, say it out loud at planning, and reference it at the daily standup and the sprint demo so it stays visible the whole sprint.
Story Assignment
How are stories assigned to team members during sprint planning?
Why it matters: Stories assigned by a manager or Scrum Master rather than chosen by the team tend to get less ownership and slower problem solving when something goes wrong. Self assignment signals a team that understands its own capacity and is accountable for its own commitments.
To improve your score: Let team members pick up stories that match their skills and availability during planning, and reserve manager assignment for genuine exceptions rather than the default.
Sprint Length
What is the standard length of a sprint for this team?
Why it matters: Shorter, consistent sprint lengths, typically two weeks, create tighter feedback loops and make estimation easier over time because the team has more data points. Sprints that stretch to three or four weeks often mask planning or readiness problems instead of solving them.
To improve your score: If sprints run longer than two weeks, look at why. Usually it is a backlog readiness or dependency problem, not a true capacity constraint, and shortening the sprint will expose it.
Velocity-Based Commitment
Does the team size its sprint commitment against actual historical velocity rather than gut feel?
Why it matters: Teams that commit based on optimism or pressure instead of their own track record tend to over-commit, which erodes trust with stakeholders and burns out the team trying to hit an unrealistic number. Historical velocity gives the team an honest, data-backed ceiling for what is realistic.
To improve your score: Track velocity for at least the last three to five sprints and use that range, not a single ideal sprint, as the starting point for how much the team takes on.
Dependency Identification
Are cross-team or external dependencies identified and discussed during sprint planning, before the sprint begins?
Why it matters: A dependency that surfaces mid-sprint, instead of during planning, almost always costs more time to resolve and can block a story the team already committed to deliver. Naming dependencies up front lets the team sequence work around them or flag the risk to stakeholders early.
To improve your score: Add a standing planning question, does this story depend on another team or an external system, and assign an owner to track any dependency the moment it is identified.
Technical Debt Capacity
Does the team reserve a portion of its sprint capacity for technical debt and defect work rather than planning at full feature capacity?
Why it matters: A team that plans every sprint at 100 percent feature capacity has no room to address the debt and defects that inevitably pile up, which slows delivery over time even as short-term output looks strong. Reserving capacity keeps the codebase healthy enough to keep moving fast.
To improve your score: Set a standing capacity allocation, for example 10 to 20 percent of the sprint, for technical debt and defects, and protect it the same way the team protects feature commitments.
Sprint Readiness
How many sprints ahead is the backlog ready to pull from?
Why it matters: A team that only has one sprint of ready work is one blocked story away from a scramble. A backlog that stays several sprints ahead gives the team room to plan around dependencies, vacations, and shifting priorities without derailing commitment.
To improve your score: Set a standing target, such as three sprints of ready backlog, and treat backlog refinement as a protected recurring event rather than something squeezed in when there is time.
Retrospective Follow-Through
Are action items from the previous Sprint Retrospective referenced or addressed during sprint planning?
Why it matters: A retrospective that produces action items nobody looks at again is not actually improving anything, it is just a recurring meeting. Bringing those action items into the next planning event is what turns a lesson learned into an actual change in how the team works.
To improve your score: Open sprint planning with a quick check on open retrospective action items, and either schedule them into the sprint or explicitly decide to defer them, do not let them quietly disappear.
Confidence Check
Does the team do an explicit confidence check or gut-check vote on its sprint commitment before planning closes?
Why it matters: Silence at the end of planning is often mistaken for agreement, when in reality individual team members may have real doubts about the commitment that never get voiced. A visible confidence check surfaces hesitation while there is still time to adjust the plan.
To improve your score: End every planning event with a simple confidence vote, such as fist of five, and treat any low score as a signal to dig into what is driving the doubt before locking in the commitment.
Sprint Demo
Does the team consistently and reliably hold a sprint demo or review?
Why it matters: The demo is the moment stakeholders see real progress instead of a status update, and it closes the loop between what was planned and what actually shipped. Skipping demos, even occasionally, erodes stakeholder trust and removes the feedback that should shape the next sprint’s planning.
To improve your score: Put the demo on the calendar as a recurring, non negotiable event tied to the end of every sprint, and hold it even when there is only partial work to show.