Capacity Planning Guide

Free Planning Tool

Capacity PlanningGuide

How the Capacity Planner works, the assumptions behind it, and when to move from the baseline to real velocity.

Open the Capacity Planner

Capacity Planning Guide

Capacity is the honest answer to one question: how much work can this team, or this ART, take on in the next Iteration or PI without burning out or breaking promises? This guide explains how the planner gets to that number and how to read what it tells you.

How the planner works

Every calculation follows the same four steps, for each Iteration:

1. Count the people. Each team member is listed by role with an allocation percentage. A full-time developer is 1.0, a tester shared across two teams at 50% is 0.5. Added together, that is the team’s counted FTE. You can leave the Scrum Master and Product Owner out of the math, which is common when capacity is sized from the people who build and test the work.

2. Start from a gross number. Pick one of the three methods below.

3. Take out support and unplanned work. These are percentages you set based on what your team actually sees.

4. Hold back a planning buffer. What remains is plannable capacity, the number to commit against. The buffer is the room you leave on purpose for the unexpected.

The three methods

New team baseline (points).

How it works: 8 points for each full-time developer or tester per 2-week Iteration, adjusted for part-timers, then minus 1 point for each person-day off for holidays, vacation and other absences. Holidays count once for every counted person, so one holiday on a team of 5.5 FTE removes 5.5 points. This is the starting guideline SAFe gives for teams with no historical data, as summarized by Xebia. When to use it: a new team, a newly formed ART, or a team whose makeup has changed so much that its old velocity no longer applies.

Historical velocity (points).

How it works: start from the average points the team has actually completed per Iteration, then scale it down for time off. If the team normally has 55 person-days available and 5 are lost to PTO, the planner uses 50/55 of the average. When to use it: any team with a few Iterations of stable history. Real velocity reflects how your team actually works, which no rule of thumb can.

Hours.

How it works: each person’s focus hours per day, times allocation, times working days, minus hours lost to time off, minus the share of time spent in Events. When to use it: teams or organizations that plan in hours, or mixed teams where points are not yet trusted. SAFe does not require one unit of measure. What matters is that the team agrees on one (Scaled Agile).

Assumptions to know

Iteration length. The 8-point baseline is written for 2-week Iterations. For 1, 3 or 4-week Iterations the planner scales it in proportion (4, 12 or 16 points per FTE). That scaling is a SIG planning assumption, not part of the published guideline, so treat it as a rough start.

Events in points-based methods. In the baseline and velocity methods, normal Event time is already part of the starting number, so the planner does not subtract it again. Only the hours method has a separate Events setting.

The IP Iteration. When the last Iteration is marked as the IP Iteration, its capacity is shown but counted as zero for planned feature work.

Status flags. The planner compares planned load to plannable capacity (after the buffer). Under 70% is flagged Under, 70% to 100% is Healthy, and anything above 100% is Over. The 70% line is a SIG tool setting to prompt a conversation, not an industry benchmark. The PI-level status only counts Iterations where you entered planned load, so a blank Iteration never hides an overloaded one.

Privacy. Everything you type stays in your browser. Nothing is saved between visits. Only the summary in the report form is sent to SIG, and only when you submit it.

When to switch from the baseline to real velocity

The baseline is a starting point, not a standard.

Why it matters: the 8-point guideline exists for teams that have no historical data yet. Once a team has its own completed Iterations, its real velocity is a far better predictor than a formula. Keeping the baseline too long can lock a team into a number that is either too optimistic or too cautious.

What to do: after three or more Iterations with a reasonably stable team and consistent estimation, switch the team to Historical velocity and use the average of those Iterations. Switch back to the baseline only if the team changes significantly, for example when half the members are new.

Worked example

An illustrative team, not real client data.

A team plans a PI of five 2-week Iterations, with the last one as the IP Iteration. It has four full-time developers, one full-time tester and one tester shared at 50%, plus a Scrum Master and a Product Owner who are left out of the math. Counted FTE is 5.5, so the baseline is 5.5 x 8 = 44 points per Iteration. Support work is set to 10%, unplanned work to 0% and the planning buffer to 20%, so plannable capacity is gross x 0.9 x 0.8.

IterationTime offGrossPlannablePlanned loadStatus
13 PTO person-days4129.528Healthy (95%)
21 holiday (5.5 person-days)38.527.731Over (112%)
34 training person-days4028.825Healthy (87%)
42 PTO person-days4230.230Healthy (99%)
5 (IP)None440–IP Iteration
PI total205.5116.3114Healthy (98%)

What it shows: the PI as a whole fits, but Iteration 2 does not. The holiday takes 5.5 points out of that Iteration, and the plan did not account for it. Moving 3 or 4 points of work from Iteration 2 into Iteration 3 brings every Iteration into the healthy range without changing the PI scope.

Reading your results

Over. Planned load is higher than plannable capacity. Expect carryover, overtime or missed PI Objectives unless something moves. Look first at Iterations with holidays or heavy PTO.

Healthy. Load fits with the buffer intact. That is the goal.

Under. Load is well below capacity. That can be intentional slack for learning or support, or it can be a sign the backlog is not ready. Know which one it is before PI Planning.

The ART view. Adds plannable capacity and planned load across every team. One team being over while another is under is a cue to look at how work is distributed, and a common topic in PI Planning. Teams that plan in hours and teams that plan in points are totaled separately.

Frequently asked questions

Why not just use Jira?

Jira is where the work lives, and it should stay there. This planner answers a question that comes before the work is loaded: how much can we realistically take on, once holidays, shared people, support load and a buffer are in view? It also gives you one ART-level picture even when teams configure their tools differently. Use it before and during PI Planning, then load the plan into Jira.

Should the Scrum Master and Product Owner count?

The planner lets you choose. A common approach is to size capacity from the people who build and test the work. Xebia’s example of the 8-point method counts only the developers and testers on a seven-person team that also has a Product Owner and Scrum Master (Xebia). If your Scrum Master or Product Owner also picks up stories, count them at the share of time they actually spend on that work.

How big should the planning buffer be?

There is no single right number. Planning to 100% leaves no room for the unexpected (Scaled Agile). The planner starts at 20% so the effect is visible. Adjust it to match how much unplanned work your team really absorbs, and revisit it each PI.

Can I compare points between teams?

Only with care. Points are relative to the team that estimates them. The ART view adds them up to support planning conversations, not to rank teams.

Is my data saved?

No. The planner runs in your browser and nothing is stored between visits. If you want to keep your plan, download the PDF or CSV report.

Sources

Xebia, Capacity Planning in an Agile Scrum Environment: the 8-point guideline attributed to SAFe for teams without historical data, adjustment for part-timers, and a worked example counting developers and testers.

Scaled Agile Framework, Iteration Planning: Iteration Planning is informed by team capacity and historical velocity.

Scaled Agile, Planning to 100% Capacity? Don’t Do It: SAFe does not prescribe a unit of measure, and the case for planning below 100% capacity.